With suitable diagrams briefly explain the two methods of placing concrete underwater described in class. The two methods are:

Underwater concrete placing requires special considerations to prevent segregation, washout, and maintaining workability and concrete quality. The required two methods are described below.
In this method, concrete is loaded into a container called bottom dump bucket. This bottom dump bucket is lowered into the water to its placement position. Once it has reached the desired location, the bottom of the bucket is opened and the whole concrete is dumped slowly.
This is a very popular method of placing concrete underwater that involves a hopper (funnel-like object) and a tremie pipe. The hopper is connected at the top of a tremie pipe which is aligned vertically and transports concrete directly to the placement site via gravity. The pipe is sealed at the bottom to prevent water from entering. A crane keeps the setup stable while concrete is poured into the hopper from a concrete truck. Afterwards the tremie pipe is gradually lifted as concrete gains required strength and gets discharged.